Client: Grupo Mexico ASARCO
Location: Hayden, Arizona
Major smelter retrofit to meet new US EPA SO2 NAAQS.
GCT developed the project from concept through detailed engineering and implementation to reduce SO2 emissions by >90% and to achieve the new ground-level concentration limit of 75 ppb on a 1-hour average.
Key Project Elements:
- Replace five existing converters with three larger converters, complete with controls, feed systems, mouth burners, ladles, and tuyere punchers
- Improve hooding and off-gas collection systems to minimize potential fugitives and achieve >99% SO2 fixation
- Install new ESP, fans, water-cooled hoods, secondary hoods, and damper controls
- Retrofit 1911-era building to accommodate new larger converters, ancillary equipment, and install a roof canopy system for tertiary ventilation
- Upgrade plant infrastructure, including blast air blowers, compressed air, cooling towers, and electrical substation
- Install high-efficiency dry lime scrubbing on two baghouses
Conceptual Engineering 2010
Basic Engineering 2011-2012
Detailed Engineering 2012-2013
Construction Phases 2016-2018
Commissioning 2018