Client: South32 – Cerro Matoso
Location: Colombia
Preliminary and basic engineering of a new off-gas system for Electric Smelting Furnace #1 and #2.
Key Project Elements:
- Primary and secondary fume collection design
- Double capacity of existing secondary baghouse
- Redirect primary and secondary gases to expanded secondary baghouse
- Basic engineering – Process, mechanical, and civil/structural
- Equipment sizing, specification preparation, and bid evaluation
- Commissioning and performance testing
Preliminary Engineering EF#2 March 2006
Gas Analysis Testing EF#2 June 2006
Basic Engineering EF#2 June 2007
Commissioning EF#2 August 2008
Basic Engineering EF#1 August 2009
Detail Engineering EF#1 December 2010
Commissioning EF#1 June 2013